Getting Started

Getting started with an ADU project is what many feel is “the fun part” – you’ll think about your goals and the value an ADU will bring, look for design and layout inspiration, and start to figure out what will work on your property.

  • Clarify what you want
  • Find inspiration
  • Estimate project cost

Project Timeline

Getting Started is part of the Planning phase, which typically takes the first 1-2 months. The entire ADU project can take as little as 6 months to complete or as long as 18 months in a larger city or with a complicated project. Check with your city or town’s building department to confirm timeline for your specific project.

Planning step of timeline

FAQs

Here are a few of the most frequently asked questions about getting started:

There are two types of construction to consider and both have pros and cons, so think about the level of customization you want and how the ADU will work on your property.

Site-built ADUs
Traditionally constructed and built from scratch on your property (AKA “stick-built”), which often slows for a lot of customization and smaller changes throughout construction.

Typical benefits:

  • More options for customization
  • Can be easier to get financing and permits
  • Can be easier to place on unique properties (steep slopes, rocky terrain, small spaces)
  • Can typically be paid for phase-by-phase

Prefab, modular, and panelized ADUs
Built in a factory, then shipped to your site and assembled or placed on a foundation. Some companies provide “turnkey” service with support through the entire process (permitting, construction, etc.). If not, you’ll need to hire other professionals to help.

Prefab ADUs are categorized based on how they are built and inspected.

  • Partially fabricated (panelized, framing kits) Parts of the ADU are built off site at a factory, and construction follows a traditional site-built pattern. Local inspectors check work at different stages and a local general contractor and their crew are responsible for putting all the pieces together and passing inspections.
  • Prefabricated (modular, manufactured, factory-built) The ADU is built and inspected for building code off site at a factory, then delivered and put in place on your property by a crane or tow. Local inspectors only check work like foundation and utility hook-ups. These types are all built similarly but are called different things based on what building code they meet (state, federal, etc.).

It’s important to note that a prefab ADU project may cost the same as site-built ADUs when you factor in transportation, crane, foundation, and sales tax, which can end up being 20-40% of the total cost. When you get in touch with prefab companies, be sure to ask what is included in the price. Some companies do offer a lower price point.

Typical benefits:

  • Lower design and engineering costs
  • More clarity on what you’ll get in the end
  • Faster construction with less on-site disruption
  • Quality inspections from the start
  • Fewer permits and inspections

State law defines “protected use ADU” (PUADU) as a type of ADU that must be allowed anywhere a single-family home can be built, whether by default or by special permit (note that this law does not apply in Boston). This means a municipality cannot require a special permit, waiver, variance, or other zoning relief or discretionary zoning approval for a PUADU that meets that definition of a Protected Use ADU.

PUADUs can be up to 900 square feet or half the gross floor area of the primary dwelling, whichever is smaller, as long as it can fit on the property and meet local regulations about setbacks and other details.* They must have sleeping, cooking, and sanitary facilities and a separate entrance from the primary home. PUADUs are still subject to State Building Code, Fire Code, Energy Code, Massachusetts Lead Law, and all other state health and safety laws, including the State Environmental Code. Every city or town can set their own rules for setbacks (distance from the property line and other structures) and dimensional standards (including size, height, and lot coverage) as long as those requirements are reasonable in accordance with state law and the ADU regulations. For more information on what dimensional standards and setback requirements can be required for a PUADU, visit Accessory Dwelling Unit (ADU) – FAQs | Mass.gov.

ADUs that do not meet the definition of a PUADU may still be allowed but will likely require additional review and permitting.

* Gross floor area is defined in the ADU regulations as the square footage of all stories of the building, including basements and lofts, but excluding garage parking, attics, enclosed porches, and crawl spaces. You should confirm any calculations or numbers with municipalities’ building department and trusted building advisors.

Building an ADU is an investment of time as well as money. Outside of Boston, most ADUs take 6-10 months from design through construction. In Boston, the process is more like 10-18 months. Of all ADU types, conversions of existing interior space are generally the fastest.

  • Planning (setting goals, learning the rules, budgeting): 1-2 months
  • Design: 1-2 months
  • Permitting: 1-2 months for a Protected Use ADU (see FAQ: What is a Protected Use ADU?) outside of Boston, 3-8 months for an ADU in Boston
  • Construction: 4-6 months

Move-in step of timeline

Check with your city or town’s building department to confirm timeline for your specific project.

The following are rough estimates for various kinds of projects, including site work and construction:

Project TypeTypical Cost Range
2BR Detached ADU$250,000-$450,000
Studio Detached ADU$200,000-$300,000
2BR Attached ADU$235,000-$360,000
Interior Conversion ADU$120,000-$270,000

The final number can vary widely and depends on many factors including:

  • ADU size and type
  • Design features and fixtures
  • Site conditions (slope, fire access, foundation complexity, utility connections)
  • Septic and stormwater details
  • Geographic location (urban vs. rural, specific location policies)

See the Budgeting page for more detailed information on typical cost ranges and financing.

In most cases, you’re not required to tell your neighbors about your ADU. But some projects may require a special zoning variance or other permit that could require a public hearing or notice (note: variances and special permits cannot be applied to a Protected Use ADU).

Regardless, it’s always a good idea to communicate with your neighbors early in the process. Your project will run more smoothly if they are kept informed, and they may have great ideas for your project!

If you live in a Neighborhood or Homeowners Association, talk with your representative or board early in the process because they may have guidelines you’ll need to know for design and construction.

There are many benefits to building an all-electric ADU, including improved indoor air quality, lower environmental footprint, and easier integration with renewable energy technology. An all-electric ADU tends to cost less upfront than a similar ADU with a gas hookup, because extending a gas line to an ADU can be expensive and complicated.

You may look into the following technologies for heating, cooking, and hot water in your ADU:

Building an all-electric ADU also makes you eligible for between $15,000-25,000 in incentives from Mass Save. ADUs that use propane, oil or gas for heating, cooking or hot water are not eligible for incentives. If you want to offset electrical loads with renewable energy, you might be able to add solar panels (see more about solar electricity here).

In most parts of Massachusetts, property owners are allowed to build a Protected Use ADU (PUADU) meeting certain characteristics (see FAQ: What is a Protected Use ADU?). You can build a PUADU in any zone where single-family homes are also allowed, including commercial or multi-family districts where you can build a single-family home – meaning you can add an ADU to a single-family home, a duplex, a triple decker, or a multi-family structure.

Your local community may choose to adopt rules that make some of these rules even easier (for instance, they may let you build a larger ADU). If a city or town chooses to allow more than one ADU on a property, it will still always require a special permitting process.

In most of Boston, ADUs converted from space already inside the home can be added to a 1-, 2- or 3-family home without zoning approval but the owner is required to live on the property. Attached and detached ADUs (including conversions of garages) are technically not considered an ADU by the city and require a much more in-depth zoning and permitting review process. See the Boston ADU website for more details.

In the Mattapan neighborhood of Boston, rules are more permissive. Owners of 1-, 2- or 3-family homes in this area can add up to one “non-detached ADU” and one detached ADU to the property (depending on maximum units per lot that are allowed in your subdistrict). The property owner is required to live on the property. “Non-detached ADUs” are defined as attached and/or conversion ADUs that add some footprint onto the existing home through a bump-out, extension, or other kinds of additions. See the City’s Research Your ADU Options page for more details.

Resources for Getting Started

Use your address to see conditions and details for your property.