FAQ: How long does construction take?

Traditional stick-built construction will take 6-10 months, though this will vary depending on the specifics of the project. Stages of stick-built construction include:

  • Site preparation: 1-2 months
  • Foundation: 1 month
  • Walls, roof, doors: 1-2 months
  • Plumbing & electrical: 1-2 months
  • Insulation & drywall: ½-1 month
  • Fixtures & finishes: 1-2 months
  • Final touches: ½-1 month

Modular construction is typically quicker than traditional construction. A factory typically needs a few months to order all the materials and components, then takes about a month to assemble them while the site and foundation is being prepared. The modular “boxes” are often delivered and assembled within a day or two, and then the local contractor can take 1-3 months to finish any remaining items, including siding, custom items, landscaping, drywall connecting the boxes and painting.

Check with your city or town’s building department to confirm timeline for your specific project.