Construction
Permit in hand, you’re ready to break ground and see your project become a reality! From site preparation to passing your final inspection, you’ll stay in touch with your contractor and make final decisions about project details.
- Get bids
- Hire a contractor
- Understand everyone’s roles during construction
Project Timeline
The Construction phase typically takes 4-6 months. The entire ADU project can take as little as 6 months to complete or as long as 18 months in a larger city or with a complicated project. Check with your city or town’s building department to confirm timeline for your specific project.
FAQs
Here are a few of the most frequently asked questions about permitting:
What’s the difference between a site-built and a prefabricated or manufactured ADU?
There are two types of construction to consider and both have pros and cons, so think about the level of customization you want and how the ADU will work on your property.
Site-built ADUs
Traditionally constructed and built from scratch on your property (AKA “stick-built”), which often slows for a lot of customization and smaller changes throughout construction.
Typical benefits:
- More options for customization
- Can be easier to get financing and permits
- Can be easier to place on unique properties (steep slopes, rocky terrain, small spaces)
- Can typically be paid for phase-by-phase
Prefab, modular, and panelized ADUs
Built in a factory, then shipped to your site and assembled or placed on a foundation. Some companies provide “turnkey” service with support through the entire process (permitting, construction, etc.). If not, you’ll need to hire other professionals to help.
Prefab ADUs are categorized based on how they are built and inspected.
- Partially fabricated (panelized, framing kits) Parts of the ADU are built off site at a factory, and construction follows a traditional site-built pattern. Local inspectors check work at different stages and a local general contractor and their crew are responsible for putting all the pieces together and passing inspections.
- Prefabricated (modular, manufactured, factory-built) The ADU is built and inspected for building code off site at a factory, then delivered and put in place on your property by a crane or tow. Local inspectors only check work like foundation and utility hook-ups. These types are all built similarly but are called different things based on what building code they meet (state, federal, etc.).
It’s important to note that a prefab ADU project may cost the same as site-built ADUs when you factor in transportation, crane, foundation, and sales tax, which can end up being 20-40% of the total cost. When you get in touch with prefab companies, be sure to ask what is included in the price. Some companies do offer a lower price point.
Typical benefits:
- Lower design and engineering costs
- More clarity on what you’ll get in the end
- Faster construction with less on-site disruption
- Quality inspections from the start
- Fewer permits and inspections
How do I find a contractor?
If you are building a site-built ADU from scratch on your property and you’re not using a design/build firm, you will need to find a contractor to take over for the construction phase of your ADU.
First, you’ll solicit bids – ideally at least three for comparison. Then you can begin selecting your contractor. Before you hire a contractor, make sure to check their license and insurance and when they present you with a contract, review everything carefully.
The state runs the Home Improvement Contractor (HIC) program with many more resources on finding and hiring a contractor. You can also see our Pioneer Valley ADU Accelerator page for a list of modular and panelized designs and companies that work in the Pioneer Valley region of the state and beyond.
How long does construction take?
Traditional stick-built construction will take 6-10 months, though this will vary depending on the specifics of the project. Stages of stick-built construction include:
- Site preparation: 1-2 months
- Foundation: 1 month
- Walls, roof, doors: 1-2 months
- Plumbing & electrical: 1-2 months
- Insulation & drywall: ½-1 month
- Fixtures & finishes: 1-2 months
- Final touches: ½-1 month
Modular construction is typically quicker than traditional construction. A factory typically needs a few months to order all the materials and components, then takes about a month to assemble them while the site and foundation is being prepared. The modular “boxes” are often delivered and assembled within a day or two, and then the local contractor can take 1-3 months to finish any remaining items, including siding, custom items, landscaping, drywall connecting the boxes and painting.
Check with your city or town’s building department to confirm timeline for your specific project.
How to Build Your ADU
Keep in Mind: Often, people who are their own general contractors have a difficult time. Building an ADU is more like building an entire home than a renovation. If you’re working with a design/build team or have hired a general contractor, they’ll manage the project (including contract negotiation, payment schedules, quality checks, and working with local departments and staff and other agencies). While it may cost more up front, you might save a lot of money by reducing delays or change orders, and get your ADU rented sooner too.
In the Pioneer Valley?
Pioneer Valley ADU Accelerator provides technical support for homeowners that are interested in building an all-electric, modular or panelized detached ADU in the Pioneer Valley.
STEP 1 Hire Your Contractor
Note: The state runs the Home Improvement Contractor (HIC) program with many more resources on finding and hiring a contractor.
Site-built ADUs: If you are not using a design/build firm, you will need to hire a contractor for the construction phase of your ADU. You will use drawings from your designer to get bids from contractors and make sure you are specific about what you want each bid to include (license details, insurance information, examples of past work, etc.). Your design team may be able to help you with this.
It’s a good idea to select between at least three bids, and it’s okay to ask contractors clarifying questions about their bid. Your designer may be able to help you compare the bids. It’s a good idea to reach out to references and to consider your personal interactions with the contractor – you’ll want to feel like you work well together and that they understand your goals.
Prefab/modular/panelized ADUs: The manufacturing team or whoever you worked with to select your ADU will walk you through the installation/assembling process and what needs to happen for site preparation and utility hookups. They will let you know if any additional professionals/contractors need to be hired.
STEP 2 Monitor Construction
Once you have building permits, the contractor you hire will lead the construction of your ADU. Be sure you have all funding in place before you start construction.
While your contractor will lead the construction process, you will have the following responsibilities:
- Keep in touch with your contractor and set up a schedule for checking in.
- Regularly walk through the construction area to monitor the quality of the work and make sure the work is progressing the way you expect.
- Be prepared to make decisions about the details—light fixtures, appliances, and other materials—in a timely manner so your contractor can stay on schedule.
- Follow the contract you agreed to, including any changes as described specifically in a change order form.
- Although your contractor will usually arrange the required city or utility inspections, it is your responsibility as the property owner to make sure that the inspections are conducted as required.
Resources
STEP 3 Get Inspections
During construction, your ADU will be inspected multiple times to ensure it is being built according to the permitted plans (typical inspections include foundations/footings, framing, electrical/plumbing, and exterior finishes).
Generally, it is your and your contractor’s responsibility to schedule all required inspections. For a list of inspections and how to schedule, contact your Building Department. After your final inspection is approved, you may be issued a certificate of occupancy. Your ADU is ready for move-in!